Alvediston Community Scheme

Scheme Information

Wessex Internet is excited to announce that we are implementing a pure fibre community scheme in Alvediston. This will upgrade our already superfast wireless services in the area to ultrafast fibre.

Following a community event held in September 2018, we have since had a community scheme approved by DCMS.

Construction is planned for January 2019. Once the majority of the network build is complete, we will be in touch to book you in for a fibre installation!

Further updates will be posted here.

Latest Update

26/02/2019:

We have now begun customer installations and we will continue to contact customers with regards to remaining garden work and available installation dates.

07/02/2019:

Our Comms box is now live! We are starting to arrange installations for next week for those who have had their garden work completed.

05/02/2019:

We are continuing with Garden works this week as well as working on the new comms cabinet. The new comms cabinet should be up and running by the end of the week and this means we can start arranging for our installs team to come and get you up and running, we will be in touch to arrange your installation

29/01/2019:

We have started Garden works in the area and will be continuing with the network build this week. We are aiming for the network to be made live the week commencing the 11th February with installations to follow that week

18/01/2019:

This week we have laid 5km of fibre around the village and will be returning next week to continue the network build. Our garden work team will also be starting garden works and they will be in touch with each registration to discuss this further

11/01/2019:

We managed to get our directional drill to Alvediston and complete 1 of the road crossings this week! We will be back next week with our mole plough to continue the network build

Current Status

Project Statistics & Timeline

%

Required Registrations
Required Registrations

%

Planning & Agreements
Planning & Agreements Complete

%

Core Network Constructed
Construction Complete
Current Status

Core Network Construction